Rural school with 125 children grade 1-11 from poor families and 22 teachers make use of the new facilities.
Villagers who are living here is very poor, and some parents of the children working as daily labours in vegetable farms and some others working as daily labours in the town. Inside school no water at all.
Realized, water and sanitation facilities:
Construct a new dug well with concrete ring elements, construct 4 low concrete stands, well cleaning, construct well cover, supply 5.000L and 2.000L water tanks, supply electric water pump and electricity cable, construct pump house and supply electricity panel board, construct total pipeline system in school premises and connected to the existing school buildings and sanitary facilities, construct 5 hand washing units (1 unit has 4 taps), construct 5 tap posts, extend the pipeline system to the primary school too, paint all our constructions.
Parents and children help: transport materials from gate to construction sites, digging for the piping.
We had to spend more money than we estimated because,
• We did estimate on end of the year 2018 for the project and we could not finished the project within the deadline due to Easter attack in year 2019, and landslides due to the heavy rain in middle of the year 2019 and also the COVID 19 pandemic. And by the year 2020/2022 the prices of every material increased more than 75%.
• Because of the COVID 19 pandemic we had to restart the project several time.
• Construct extra 4 low concrete water stands and supply new 2.000L and 5.000L water tank.
• Construct extra 3 hand washing units and 5 tap posts.
• Construct a stone wall for protection of the well.